Golden Horse Casino Pietermaritzburg : Borehole Siting, Drilling and Yield Testing

Project completion date September 2017

Client’s Problem: Looking for an affordable way to substitute the cost of water for the establishment, as well as provide water during municipal shortages.

Client’s Requirements: Carry out siting, drilling and yield testing of new borehole to substitute the water consumption for the Hotel and surrounding amenities.

Borehole Location: In Parking lot.

Drilled depth: 150 meters Below ground level

Steel casing installation depth: 80 meters Below ground level- Due to unstable geology and borehole constantly collapsing.

Yield Test results: Still to be tested.

Pump equipment installed: Yet to be equipped.

Rising main pipe: n/a

Control Panel: n/a

Filtration: n/a